CONSTRUCTION UPDATES

Opal block

Tiles

3 to 6 floors Tiles works completed, 7th floor work in progress, except 5 series flats

Internal Brick work

1 to 19 floors completed

Plumbing work

1 to 17 floors completed

Water proofing

1 – 16 floors completed

PVC

till 19 floor completed

Painting Work

2 to 19 floor 1st coat putty work completed Final coat putty work in progress

Windows fixing

1 to 19 floor completed

Electrical

routing cleared till 19 floors, wiring work is in progress in 5th floor

Tanzanite Block

Flat Handovers started.

Quartz- Block

Flat Handovers started.

Diamond –Block

19 floors Structure work completed, Internal Brick work in progress

Ruby Block

Flat Handovers started

Emerald–Block

Structure Work

19 floors Structure work completed

Internal brick work

brickwork completed till 18 floors

Plumbing

Plumbing work 3rd to 10th floors & 15th to 18th floors completed

Electrical Works

electrical routing cleared till 18 floors

Windows fixing

windows fixing 3rd to 10th floors completed

Water Proofing

water proofing 3rd to7th floors completed

Topaz Block

19 floors Structure work completed, Internal Brick work in progress

Aquamarine- Block

Ground floor Structure work in progress